Central Customs Administration: cooling in the basement of an old building

In brief. In a historic building in central Moscow, two 500 kW Thermax LT-14 C absorption chillers run on the heat of five Capstone C200 microturbines. The chillers were brought in parts and assembled in the basement. Part of the cooling goes to the server rooms.

In the historic building of the Central Customs Administration in Moscow, a chiller plant has been built on the heat of five Capstone C200 microturbines. Two Thermax LT-14 C lithium bromide absorption chillers of 500 kW each cool water for air conditioning, and part of the cooling goes to the server rooms. The chillers were delivered disassembled and assembled in the basement.

Parameter Data
Industry Government institution, historic building
City Moscow
Generation 5 Capstone C200 microturbines of 200 kW each, heat recovery unit, boiler house and heat recovery boilers
Heat Hot water from the boiler house and heat recovery units
Absorption chillers 2 × Thermax LT-14 C, 500 kW each, water 12/7 °C
Heat rejection 2 closed-circuit wet cooling towers
What the cooling is for Air conditioning of the administrative building, part of the cooling for server rooms
Our work Supply, rigging, installation supervision, commissioning

What was the task?

The building stands in the historic center, where there is not enough electrical capacity. Compressor chillers would have required even more electricity, so cooling for the building and the server rooms is made from the heat of a mini power plant on microturbines. It was commissioned around 2015.

How does the scheme work?

Microturbines and an absorption chiller

The microturbines produce electricity, and their heat goes into hot water through a heat recovery unit. The water, together with heat from the boiler house, drives the absorption chillers, which supply cooling to the building network.

Several microturbines produce electricity; their exhaust is collected in a common header and goes into an exhaust-fired Thermax chiller. The scheme is used in buildings and data centers.

What was difficult?

The basement of the old building, with its narrow passages, cannot take a whole chiller. Each absorption chiller was delivered disassembled, in two parts, and assembled on site: this required complex rigging and installation supervision.

What was the result?

The chiller plant was successfully started up. The general contractor's letter of 29 July 2015 confirms on-time delivery, rigging, installation supervision and commissioning.

Site photos

Absorption chiller in the basement
Absorption chiller in the basement
Closed-circuit cooling tower on site
Closed-circuit cooling tower on site
Cooling tower on the roof with a service ladder
Cooling tower on the roof with a service ladder
Two shells of the absorption chiller in the basement
Two shells of the absorption chiller in the basement
Insulated absorption chiller after assembly
Insulated absorption chiller after assembly
Five microturbines in one row
Five microturbines in one row

General contractor's letter

Letter of thanks: Nord Kraft LLC, general contractor for the energy center construction, not the building owner
Letter of thanks: Nord Kraft LLC, general contractor for the energy center construction, not the building owner

Letter of 29 July 2015, ref. No. 1173: thanks for the on-time delivery of two LT 14 C absorption chillers, rigging, installation supervision and commissioning.

If you have a similar task, order a feasibility study or estimate the figures in the calculator. Related pages: microturbines, business centers and hotels and trigeneration for data centers. The chiller design is described on the page Thermax absorption chiller, and other examples are collected in the "Our projects" section, along with many others.

What our customers say

150 letters of thanks · 350+ major projects · 1,000+ customers · in business since 2011. These are real letters from customers; many others are on the references page.

All references and letters All projects

Let us calculate trigeneration for your site

An engineer will put together the scheme and select the equipment, and you get a feasibility study. Free of charge, no obligation.

Get a feasibility study