Customer Reviews of Trigeneration and Thermax Absorption Chillers

In brief. Six letters from 2013–2020, three from site owners and three from contractors. The letters confirm delivery, schedules and equipment operation, but not the payback period.

Here are six letters for sites where a cooling circuit based on Thermax absorption chillers and NCT equipment works with gas engines. Three letters were signed by site owners, three by contractors and general contractors. We state who signed because a contractor's letter confirms its own part of the work, not the owner's operating experience. None of the letters gives a payback period: only on-time delivery, commissioning and equipment operation.

Who confirmed what?

Site Who signed Date What is confirmed
Syry Kubani Owner, executive director 4 August 2020 On-time delivery, water outlet down to 2 °C
Osobino cogeneration unit Site contractor 15 July 2014 Absorption chiller delivered on time and in full
TsTU, Moscow Energy center general contractor 29 July 2015 Delivery, installation supervision, commissioning
Mikran, Tomsk Energy center owner 15 October 2014 Shipment a month ahead of schedule
Aray City Mall Owner, technical director no date on the scan Trouble-free operation, electricity savings
Davydovka cogeneration unit Site contractor 15 November 2013 Absorption chiller delivered on time and in full

What do customers write?

Syry Kubani dairy plant

Letter No. 124 of 4 August 2020 was signed by the plant's executive director, that is, the site owner. He confirms that a 3,500 kW Thermax lithium bromide absorption chiller and NCT VR4-4-ML3-T cooling towers were delivered on time: the absorption chiller in 20 weeks, the cooling towers ahead of schedule. Commissioning confirmed the declared performance. The machine cools water from 12 to 7 °C and from 6 to 2 °C. More about the project in the section on food production.

Letter of thanks: Syry Kubani
Letter of thanks: Syry Kubani

Osobino cogeneration unit (Belorusneft)

Letter No. 06-2271 of 15 July 2014 is signed by ZAO Belteplomashstroy, Minsk. This is the contractor for the site, not the owner. The letter concerns the delivery of a 280 kW Thermax LT 10C absorption chiller: the work was completed in full and on time, EAEU technical regulation (TR TS) declarations were provided, and the company is recommended as a reliable supplier.

Letter of thanks: Osobino cogeneration unit
Letter of thanks: Osobino cogeneration unit

Central Customs Administration building, Moscow

Letter No. 1173 of 29 July 2015 was signed by OOO Nord Kraft, Saint Petersburg. This is the general contractor for the construction of the energy center, not the owner. The letter thanks us for the on-time delivery of two Thermax LT 14 C absorption chillers in knocked-down form for the building basement, for the difficult rigging, installation supervision and commissioning.

Letter of thanks: Central Customs Administration
Letter of thanks: Central Customs Administration

NPF Mikran, Tomsk

Letter No. 6200/k of 15 October 2014 was signed by the deputy general director of the owner of a gas-fired energy center running in trigeneration (CCHP) mode. He thanks us for the delivery of two Thermax absorption chillers and two cooling towers. Shipment took place a full month ahead of schedule, despite the cargo being held up in Belgium because of the sanctions that had just begun. The site is described in the section on industry and energy.

Letter of thanks: NPF Mikran
Letter of thanks: NPF Mikran

Aray City Mall, Kyzylorda

The letter was signed by the technical director of TOO Kyzylorda Kurylys NK, the owner of the shopping mall. There is no date on the scan; we published the news about the review on 27 February 2020. The customer thanks us for design, supply, installation supervision and commissioning: two Thermax absorption chillers (one on a gas engine, one gas-fired) with a total capacity of 2,200 kW and two NCT cooling towers operate without faults in the trigeneration system and save electricity. The letter gives no savings figures. More in the section on shopping malls.

Letter of thanks: Aray City Mall
Letter of thanks: Aray City Mall

Davydovka cogeneration unit (Belorusneft)

Letter No. 06-2171 of 15 November 2013 is also signed by ZAO Belteplomashstroy; this is a contractor, not the owner. It concerns a 651 kW Thermax LT 14C absorption chiller: the work was completed in full, within the set deadlines and in compliance with regulations, and the company is recommended.

Letter of thanks: Davydovka cogeneration unit
Letter of thanks: Davydovka cogeneration unit

What do the letters not show?

The letters tell about delivery and start-up. They do not say how the machine behaved five and ten years later, and they give no payback period. For that there are the model feasibility studies and the site pages in the projects section. We have more sites than there are letters in this section.

If you want to see the equipment in operation, look at the list in projects and send a request for a feasibility study: we will find a site with a similar task and give you the customer's contacts. Other company materials are on the colden.ru website.

Frequently asked questions

Can we see the equipment in operation and talk to the operating staff?

Yes. Besides the letters, we offer reference lists of similar projects and visits to operating sites, for example an absorption chiller at a gas turbine power plant. On request, we give customer contacts so that you can get a review by phone, not just from a scan.

Let us calculate trigeneration for your site

An engineer will put together the scheme and select the equipment, and you get a feasibility study. Free of charge, no obligation.

Get a feasibility study