Tau Galereya shopping mall: two 2,200 kW Thermax absorption chillers

In brief. At the Tau Galereya shopping mall in Saratov, two 2,200 kW Thermax 5G 6L C absorption chillers run on hot water from gas engines. The company's materials estimate the benefit at more than RUB 7 million per year.

At the Tau Galereya shopping and entertainment mall in Saratov, two 2,200 kW Thermax 5G 6L C lithium bromide absorption chillers make cooling from the heat of gas engine generator sets. The contract was signed in April 2014, and the equipment was delivered in November of the same year. We supplied the chillers and carried out installation supervision and commissioning.

Parameter Data
Industry Commercial real estate: a large shopping and entertainment mall with a cinema and a hypermarket
City Saratov
Generation Gas engines
Heat Hot water from gas engines
Absorption chillers 2 × Thermax 5G 6L C, 2,200 kW each, water at 12/7 °C
Heat rejection Rooftop cooling towers, make not stated in the materials
What the cooling is for Air conditioning of the shopping mall
Our work Supply, installation supervision, commissioning

What was the task?

The engineering logic is this: a shopping mall needs air conditioning in summer, and a 4,400 kW compressor chiller is a significant electrical load. At that time the gas engine heat is not needed for heating, so it is used to make cooling.

How does the scheme work?

The classic: gas engines and hot water absorption chillers

Two chillers take hot water from the engines and make water at 12/7 °C. The rooftop heat rejection equipment removes the chillers' heat. Without absorption chillers, the same heat would be dumped into the atmosphere in summer.

The engine jacket and exhaust heat exchanger heat water to about 90 °C. The water goes through a heat exchanger into a single-effect Thermax chiller with a COP of about 0.8. The chiller supplies 7/12 °C water to the consumer and rejects heat to an NCT cooling tower. Surplus heat is removed by dump radiators.

What was the result?

The company's materials estimate the annual benefit from using waste gas engine heat in summer at more than RUB 7 million. The calculation method was not given in open materials, so this is a guide, not a guarantee for your site.

Site photos

Three cooling towers on the roof
Three cooling towers on the roof
Cooling tower block, side view
Cooling tower block, side view
The mall building with construction cranes
The mall building with construction cranes
Thermax absorption chiller, full view
Thermax absorption chiller, full view

If you have a similar task, order a feasibility study or estimate the figures in the calculator. Related pages: shopping malls and feasibility study for a shopping mall. How the chillers work is described on the Thermax absorption chillers page, and other examples are collected in the "Our sites" section, along with many others.

What our customers say

150 letters of thanks · 350+ major projects · 1,000+ customers · in business since 2011. These are real letters from customers; many others are on the references page.

All references and letters All projects

Let us calculate trigeneration for your site

An engineer will put together the scheme and select the equipment, and you get a feasibility study. Free of charge, no obligation.

Get a feasibility study