In brief. Eight 2 MW engines cover 61% of the complex's electricity demand, and the heat of each engine goes to its own 600 TR Thermax machine.

At the Grand Venezia complex, eight 2 MW gas engines cover 61% of its electricity demand. The exhaust and jacket water heat of each engine goes to a Thermax absorption chiller: eight machines in total, with 16,877 kW of cooling.
What does the project consist of?
| Parameter | Value |
|---|---|
| Industry | Shopping mall and hotel |
| Engines | 8 gas engines of 2 MW each, 16 MW in total |
| Fuel | Natural gas |
| Heat for the machine | Exhaust at 424 °C and engine jacket water at 93 °C |
| Machine and cooling | 8 machines of 600 TR each, 16,877 kW (4,800 TR) in total |
| What the cooling is for | Air conditioning of the complex: 1 million sq ft of retail and a 200-room hotel |
Why is this example useful for a Russian site?
Here each engine has its own machine, 8 to 8. If one unit stops, the complex loses one eighth of its electricity and cooling, and the rest keep running. Small units also handle part load more easily: some of them can simply be switched off. More: trigeneration (CCHP) for business centers and hotels.
How does this kind of scheme work?
One machine takes both the exhaust and the engine jacket hot water and needs no separate heat exchangers.
Based on Thermax materials
Other projects worldwide

AT&S in Shanghai: one 1.1 MW engine and one Thermax absorption chiller give 1,160 kW of cooling in summer and 80 °C hot water in…

Berlin Airport: two Thermax chillers on engine exhaust give 2,600 kW of air conditioning cooling. A trigeneration case with…

Brevoort East residential building in New York: two Tecogen engines and a 280 kW Thermax machine that kept running through…
What our customers say
150 letters of thanks · 350+ major projects · 1,000+ customers · in business since 2011. These are real letters from customers; many others are on the references page.
Let us calculate trigeneration for your site
An engineer will put together the scheme and select the equipment, and you get a feasibility study. Free of charge, no obligation.