AT&S, Shanghai, China

In brief. One 1,160 kW Thermax machine supplies the plant with 7 °C chilled water in summer and 80 °C hot water in winter from the heat of a single engine.

AT&S, Shanghai, China

At the AT&S printed circuit board plant in Shanghai, a single 1.1 MW gas engine sends its exhaust and jacket water heat to one 1,160 kW Thermax absorption chiller. In summer the machine makes 7 °C chilled water, in winter 80 °C hot water. The source lists the benefits: lower emissions, less noise and less vibration.

What does the project consist of?

Parameter Value
Industry Electronics, printed circuit boards
Engines 1 gas engine, 1.1 MW
Fuel Natural gas
Heat for the machine Exhaust at 454 °C and engine jacket water at 81 °C
Machine and cooling 1 machine, 1,160 kW (330 TR)
What the cooling is for Chilled water at 7 °C in summer, hot water at 80 °C in winter

Why is this example useful for a Russian site?

One 1.1 MW engine and one 1,160 kW machine: the exhaust and the jacket water give roughly 1 kW of cooling per 1 kW of electricity. In winter the same machine delivers 80 °C water, so we check in advance whether this temperature schedule suits the plant's heating system. More: trigeneration (CCHP) at industrial plants.

How does this kind of scheme work?

In summer the heat goes to the machine and produces cooling; in winter it goes to heating.

In winter the heat goes to space heating, hot water and processes; in the shoulder season it is split between heating and the absorption chiller; in summer it goes into the chiller and produces 7/12 °C water. The site gets electricity all year round.

Based on Thermax materials

What our customers say

150 letters of thanks · 350+ major projects · 1,000+ customers · in business since 2011. These are real letters from customers; many others are on the references page.

All references and letters All projects

Let us calculate trigeneration for your site

An engineer will put together the scheme and select the equipment, and you get a feasibility study. Free of charge, no obligation.

Get a feasibility study