AT&S, Shanghai, China
In brief. One 1,160 kW Thermax machine supplies the plant with 7 °C chilled water in summer and 80 °C hot water in winter from the heat of a single engine.

At the AT&S printed circuit board plant in Shanghai, a single 1.1 MW gas engine sends its exhaust and jacket water heat to one 1,160 kW Thermax absorption chiller. In summer the machine makes 7 °C chilled water, in winter 80 °C hot water. The source lists the benefits: lower emissions, less noise and less vibration.
What does the project consist of?
| Parameter | Value |
|---|---|
| Industry | Electronics, printed circuit boards |
| Engines | 1 gas engine, 1.1 MW |
| Fuel | Natural gas |
| Heat for the machine | Exhaust at 454 °C and engine jacket water at 81 °C |
| Machine and cooling | 1 machine, 1,160 kW (330 TR) |
| What the cooling is for | Chilled water at 7 °C in summer, hot water at 80 °C in winter |
Why is this example useful for a Russian site?
One 1.1 MW engine and one 1,160 kW machine: the exhaust and the jacket water give roughly 1 kW of cooling per 1 kW of electricity. In winter the same machine delivers 80 °C water, so we check in advance whether this temperature schedule suits the plant's heating system. More: trigeneration (CCHP) at industrial plants.
How does this kind of scheme work?
In summer the heat goes to the machine and produces cooling; in winter it goes to heating.
Based on Thermax materials
Other projects worldwide

Berlin Airport: two Thermax chillers on engine exhaust give 2,600 kW of air conditioning cooling. A trigeneration case with…

Brevoort East residential building in New York: two Tecogen engines and a 280 kW Thermax machine that kept running through…

Cadbury plant in Lagos: one 3.7 MW engine and a gas-fired Thermax chiller give 2,317 kW of cooling at 6 °C. A trigeneration case…
What our customers say
150 letters of thanks · 350+ major projects · 1,000+ customers · in business since 2011. These are real letters from customers; many others are on the references page.
Let us calculate trigeneration for your site
An engineer will put together the scheme and select the equipment, and you get a feasibility study. Free of charge, no obligation.