Cadbury, Ikeja (Lagos), Nigeria
In brief. A single 2,317 kW Thermax chiller cools the plant even when the engine is stopped, because it can burn gas on its own.

At a confectionery plant in Lagos, one 3.7 MW Rolls-Royce engine drives one 2,317 kW Thermax absorption chiller. The chiller takes the exhaust and the jacket water and, when needed, burns gas on its own. Water leaves it at 6 °C.
What does the project consist of?
| Parameter | Value |
|---|---|
| Industry | Confectionery plant |
| Engines | Rolls-Royce, 1 engine of 3.7 MW |
| Fuel | Natural gas |
| Heat for the chiller | Exhaust, jacket water and direct gas firing (100 % backup) |
| Chillers and cooling | 1 chiller, 2,317 kW (660 TR) |
| What the cooling is for | Process cooling and air conditioning, water at 6 °C |
Why is this example useful for a Russian site?
Where gas is available, the burner replaces a separate backup chiller. At full burner output, with a COP of 1.4, the chiller needs about 180 m³/h, and this hourly limit is agreed in advance. If the engine stops because of a gas outage, the burner will be left without gas too, and the site without cooling. More: trigeneration for food plants.
How does this kind of scheme work?
The built-in burner tops up cooling when the engine is stopped or there is not enough heat.
Based on Thermax materials
Other projects worldwide

AT&S in Shanghai: one 1.1 MW engine and one Thermax absorption chiller give 1,160 kW of cooling in summer and 80 °C hot water in…

Berlin Airport: two Thermax chillers on engine exhaust give 2,600 kW of air conditioning cooling. A trigeneration case with…

Brevoort East residential building in New York: two Tecogen engines and a 280 kW Thermax machine that kept running through…
What our customers say
150 letters of thanks · 350+ major projects · 1,000+ customers · in business since 2011. These are real letters from customers; many others are on the references page.
Let us calculate trigeneration for your site
An engineer will put together the scheme and select the equipment, and you get a feasibility study. Free of charge, no obligation.