California State University, Fullerton, USA
In brief. Exhaust from a Mercury 50 turbine gives 56 % of the campus cooling, and 44 % comes from gas firing in two Thermax chillers with a total of about 9,200 kW.
The university campus in Fullerton gets about half of its electricity from its own gas turbine. The exhaust goes to two Thermax double-absorber absorption chillers. According to the case, 56 % of the cooling comes from the exhaust, and the chillers make up the remaining 44 % by burning gas directly.
What does the project consist of?
| Parameter | Value |
|---|---|
| Industry | University, campus |
| Engines | Mercury 50 gas turbine, one unit |
| Fuel | Natural gas |
| Heat for the chiller | Exhaust at 375 °C; direct gas firing in the chiller is possible |
| Chillers and cooling | 2 exhaust-fired double-absorber chillers of 1,310 TR each, 2,620 TR in total (about 9,200 kW) |
| What the cooling is for | Campus cooling and heating, hot water |
Why is this example useful for a Russian site?
56 % of the cooling from exhaust and 44 % from gas firing means the chiller is calculated as two sources. The exhaust covers the base load almost for free, while the burner share needs its own gas limit, and that cooling is no longer waste heat: its cost is calculated separately. More: trigeneration with gas turbines.
How does this kind of scheme work?
Gas turbine exhaust goes to an exhaust-fired chiller; when cooling demand is low, the gas goes to the bypass.
Based on Thermax materials
Other projects worldwide

AT&S in Shanghai: one 1.1 MW engine and one Thermax absorption chiller give 1,160 kW of cooling in summer and 80 °C hot water in…

Berlin Airport: two Thermax chillers on engine exhaust give 2,600 kW of air conditioning cooling. A trigeneration case with…

Brevoort East residential building in New York: two Tecogen engines and a 280 kW Thermax machine that kept running through…
What our customers say
150 letters of thanks · 350+ major projects · 1,000+ customers · in business since 2011. These are real letters from customers; many others are on the references page.
Let us calculate trigeneration for your site
An engineer will put together the scheme and select the equipment, and you get a feasibility study. Free of charge, no obligation.




